Slab casting started for the Virar Station for Bullet Train
short by / on Wednesday, 4 June, 2025
The first slab casting at the Virar Bullet Train station has started progressing the Mumbai-Ahmedabad Bullet Train Project. The slab, which is 50 meters in length, 35.32 meters in width, and has a thickness of approximately 300 mm, will utilise over 1555 cubic meters of concrete.